Updated:2022-12-23 16:04:00
The project involves the construction of the Gomel-Gorki main oil pipeline (length: 207 km, diameter: 530 mm) that will connect two main pipelines: Unecha-Polotsk and Unecha-Mozyr-Adamovo. Operator: OJSC Gomeltransneft Druzhba Contractor: Belorusneft, an industrial group and republican unitary enterprise (Neftespetsstroy). Commissioning is scheduled for September 2022.Ā